May 27th - Current MOT Stage - Stage 1
By: Diana Woodruff
05.27.2025
Please feel free to reach out with any questions you may have.
Ongoing Relocation Work:
- ComEd/ATT Comcast Relocation Work is ongoing.
- Storm Sewer Installation on Hunt Club Rd, north of Washington.
Upcoming Relocation Work
- Storm Sewer Installation on Washington St, south of Hunt Club
- Storm Sewer installation on Washington St, east and west of Hunt Club Rd.
- Removals, excavation, and grading for widening improvements on the east side of Hunt Club Rd and the south side of Washington St.
To stay informed with future updates, please join our mailing list.