Project Updates
Progress Overview
The Lake County Division of Transportation is getting ready to improve the intersection of Hunt Club Road and Washington Street starting in the Fall 2024. Utility Relocation Work will be on going through the Summer of 2024 in preparation for the project. Watermain and storm sewer work is anticipated to start in the Fall/Winter of 2024 with the roadway and intersection work to follow in 2025.
All Contract Updates
NO PROJECT UPDATES
At the moment, there are no project updates, please check back at a different time to see any updates. Otherwise, please sign up to the mailing list so that you receive updates as soon as possible.
All Contract Updates
January 6, 2025
January 6th – Relocation Work Update
ComEd/ATT/Comcast Relocation Work ongoing, expected completion end of January....
December 9, 2024
December 9th – Relocation Work Update
ComEd/ATT/Comcast Relocation Work ongoing, expected completion end of December....
November 25, 2024
November 25th Update – Utilities Relocation
JAWA Watermain Installation-Starting on the North side of Washington, East of Hunt Club...
November 11, 2024
November 11th Construction Update – Watermain
ComEd/ATT/Comcast Relocation Work on going, expected completion late-November...
October 30, 2024
October 30th Construction Update – Watermain
ComEd/ATT/Comcast Relocation Work on going, expected completion mid-November...
August 23, 2024
Construction Update – Watermain
Berger Contractors will be starting on the Hunt Club and Washington project with the Village of Gurnee...
All Contract 2 Updates
January 6, 2025
January 6th – Relocation Work Update
ComEd/ATT/Comcast Relocation Work ongoing, expected completion end of January....
December 9, 2024
December 9th – Relocation Work Update
ComEd/ATT/Comcast Relocation Work ongoing, expected completion end of December....
November 25, 2024
November 25th Update – Utilities Relocation
JAWA Watermain Installation-Starting on the North side of Washington, East of Hunt Club...
November 11, 2024
November 11th Construction Update – Watermain
ComEd/ATT/Comcast Relocation Work on going, expected completion late-November...
October 30, 2024
October 30th Construction Update – Watermain
ComEd/ATT/Comcast Relocation Work on going, expected completion mid-November...
August 23, 2024
Construction Update – Watermain
Berger Contractors will be starting on the Hunt Club and Washington project with the Village of Gurnee...