Project Updates
Progress Overview
The Lake County Division of Transportation is getting ready to improve the intersection of Hunt Club Road and Washington Street starting in the Fall 2024. Utility Relocation Work will be on going through the Summer of 2024 in preparation for the project. Watermain and storm sewer work is anticipated to start in the Fall/Winter of 2024 with the roadway and intersection work to follow in 2025.
All Contract Updates
NO PROJECT UPDATES
At the moment, there are no project updates, please check back at a different time to see any updates. Otherwise, please sign up to the mailing list so that you receive updates as soon as possible.
All Contract Updates
November 25, 2025
November 24th – Construction Work Update
Underground conduit installation for new traffic signal configuration at the intersection of Hunt Club Rd and…
October 27, 2025
October 27th- Construction Work Update
Underground conduit installation for new traffic signal configuration at the intersections of Hunt Club Rd and…
October 13, 2025
October 13th- Construction Work Update
Storm Sewer installation on east side of Hunt Club Rd north of Washington St
September 29, 2025
September 29th- Construction Work Update
Curb and gutter, pavement, and driveway removals on east side of Hunt Club Rd and the north side of Washington St
September 16, 2025
September 15th- Construction Work Update
Topsoil respread/grading behind curbs on all legs of Hunt Club Rd and Washington St
September 2, 2025
September 2nd – Construction Work Update
Base course widening on the east side of Hunt Club Rd and the south side of Washington St
August 22, 2025
August 18th – Construction Work Update
Concrete curb and gutter installation on the east side of Hunt Club Rd and the south side of Washington St.......
August 4, 2025
August 4th – Relocation Work Update
ComEd/ATT/Comcast Relocation Work is ongoing.......
July 21, 2025
July 21st – Relocation Work Update
Storm sewer installation and ditch grading on the south side of Washington St west of Hunt Club Rd.
June 23, 2025
June 23rd – Relocation Work Update
ComEd/AT&T/Comcast utility relocation work is ongoing
June 9, 2025
June 9th – Relocation Work Update
Removals, excavation, and grading for widening improvements on the east side of Hunt Club Rd and the south side of…
May 27, 2025
May 27th – Current MOT Stage-Stage 1
Removals, excavation, and grading for widening improvements on the east side of Hunt Club Rd and the south side of…
May 12, 2025
May 12th – Relocation Work Update
ComEd/ATT Comcast Relocation Work is ongoing, expected completion end of May
April 28, 2025
April 28th- Relocation Work Update
ComEd/ATT/Comcast Relocation Work is ongoing, expected completion end of May
March 31, 2025
March 31st – Relocation Work Update
Temporary traffic signal installations at Hunt Club & Washington, and Hunt Club & Orchard Valley. Temporary pavement…
February 18, 2025
February 18th – Relocation Work Update
JAWA, Lake County Public Works, and Village of Gurnee Watermain abandonment. Temporary traffic signal pole…
February 3, 2025
February 3rd – Relocation Work Update
ComEd/ATT/Comcast Relocation Work is ongoing, expected completion end of March....
January 20, 2025
January 20th – Relocation Work Update
JAWA Watermain Installation - Work to follow on the West & East side of Hunt Club, South of Washington.
January 6, 2025
January 6th – Relocation Work Update
ComEd/ATT/Comcast Relocation Work ongoing, expected completion end of January....
December 9, 2024
December 9th – Relocation Work Update
ComEd/ATT/Comcast Relocation Work ongoing, expected completion end of December....
November 25, 2024
November 25th Update – Utilities Relocation
JAWA Watermain Installation-Starting on the North side of Washington, East of Hunt Club...
November 11, 2024
November 11th Construction Update – Watermain
ComEd/ATT/Comcast Relocation Work on going, expected completion late-November...
October 30, 2024
October 30th Construction Update – Watermain
ComEd/ATT/Comcast Relocation Work on going, expected completion mid-November...
August 23, 2024
Construction Update – Watermain
Berger Contractors will be starting on the Hunt Club and Washington project with the Village of Gurnee...
All Contract 2 Updates
November 25, 2025
November 24th – Construction Work Update
Underground conduit installation for new traffic signal configuration at the intersection of Hunt Club Rd and…
October 27, 2025
October 27th- Construction Work Update
Underground conduit installation for new traffic signal configuration at the intersections of Hunt Club Rd and…
October 13, 2025
October 13th- Construction Work Update
Storm Sewer installation on east side of Hunt Club Rd north of Washington St
September 29, 2025
September 29th- Construction Work Update
Curb and gutter, pavement, and driveway removals on east side of Hunt Club Rd and the north side of Washington St
September 16, 2025
September 15th- Construction Work Update
Topsoil respread/grading behind curbs on all legs of Hunt Club Rd and Washington St
September 2, 2025
September 2nd – Construction Work Update
Base course widening on the east side of Hunt Club Rd and the south side of Washington St
August 22, 2025
August 18th – Construction Work Update
Concrete curb and gutter installation on the east side of Hunt Club Rd and the south side of Washington St.......


