June 23rd - Relocation Work Update

Ongoing Work:

  • ComEd/AT&T/Comcast utility relocation work is ongoing.
  • Storm sewer installation is in progress on Washington St, east of Hunt Club Rd.
  • Removals, excavation, and grading for widening improvements on the east side of Hunt Club Rd and the south side of Washington St are pending due to utility conflicts.

Upcoming Work

  • Storm sewer installation on Hunt Club Rd, south of Washington St.
  • Storm sewer installation on Washington St, east side of Hunt Club Rd.