November 24th- Construction Work Update

Ongoing Work

  • Storm Sewer installation on north side of Washington St west of Hunt Club Rd.

  • Excavation and grading for widening improvements on the east side of Hunt Club Rd south of Washington St.
  • HMA Patching on all legs of intersection.
  • Underground conduit installation for new traffic signal configuration at the intersection of Hunt Club Rd and Washington St.

  • Temporary modified urethane pavement markings on all legs of intersection.

Upcoming Work

  • Storm Sewer installation on the south side of Washington St east of White Oak Ln.
  • Construction shut down for winter.