April 27th - Construction Work Update
By: Diana Woodruff
04.27.2026
Please feel free to reach out with any questions you may have.
Ongoing Work
- HMA base course widening on the east side of Hunt Club Rd south of Washington St and on the north side of Washington St west of Hunt Club Rd.
- HMA wedging for Stage 3 MOT configuration.
Upcoming Work
- Underground conduit and foundation installation for new traffic signal configuration at the intersection of Hunt Club Rd and Washington St.
- Guardrail installation at Hunt Club Rd and Orchard Valley Dr.
- Permanent and temporary landscaping for Stage 2 along project limits.
- Sidewalk installation on the east side of Hunt Club Rd south of Washington St.
- Stage 3 MOT shift.