Ongoing Relocation Work:
- ComEd/ATT Comcast Relocation Work is ongoing, expected completion end of May.
- Storm Sewer Installation on Hunt Club Rd, north of Washington
- Bike Path construction along the west side of Hunt Club north of Washington
Upcoming Relocation Work
- Storm Sewer Installation on Washington St, west of Hunt Club
- Temporary pavement construction along the east side of Hunt Club and the north side of Washington.
- Temporary traffic signal turn on and Stage 1 MOT shift