Utility Relocation August 2024 Update
By: Rami Asfahani & Diana Woodruff
8.15.2024
Please feel free to reach out with any questions you may have.
Ongoing Relocation Work:
- North Shore Gas Relocation Work Completed by end of August.
- ComEd/Comcast/ATT Relocation Work Anticipated Completion End of October.
Upcoming Relocation Work
- Watermain and Storm Sewer Work anticipated to start in the Fall (October/November) and continue through the Winter.
- Updates on further details of locations and type of work to follow.