Construction August 2024 Update - Watermain

Ongoing Relocation Work:

  • North Shore Gas Relocation Work Complete.
  • ComEd/ATT/Comcast Relocation Work on going, expected completion early November.

Upcoming Relocation Work

  • Berger Contractors will be starting on the Hunt Club and Washington project with the Village of Gurnee Watermain Work. They will be starting at the South limits of the project on the East side of Hunt Club North of Wild Flower Lane. The contractor will be potholing utilities and drilling near watermain in the parkway. Daily intermittent lane closures may be needed from 9am to 3pm.

To stay informed with future updates, please join our mailing list.