Ongoing Work
- Storm sewer installation in center medians on Washington St east and west of Hunt Club Rd.
- Curb and gutter installation in center medians on the Washington St east and west of Hunt Club Rd and on Hunt Club Rd north and south of Washington St.
- Installation of permanent traffic signal posts and mast arms at the intersections of Hunt Club Rd and Washington St & Hunt Club Rd & Orchard Valley Dr.
Upcoming Work
- Â Backfill center medians on the Washington St east and west of Hunt Club Rd and on Hunt Club Rd north and south of Washington St.
- Install stamped concrete and gravel mulch in center medians on the Washington St east and west of Hunt Club Rd and on Hunt Club Rd north and south of Washington St.
- Permanent and temporary landscaping for Stage 2 along project limits.
- HMA surface removal of existing roadway along project limits in preparation for resurfacing.