September 2nd - Construction Work Update

Ongoing Work:

  • Base course widening on the east side of Hunt Club Rd and the south side of Washington St.
  • HMA driveways on the east side of Hunt Club Rd and the south side of Washington St.
  • Earth excavation and grading for bike path on the west side of Hunt Club Rd north of Washington St.
  • Underground conduit installation for new traffic signal configuration at the intersection of Hunt Club Rd and Washington St.

Upcoming Work

  • HMA lateral patching on all legs of Hunt Club Rd & Washington St.
  • HMA paving for bike path on the west side of Hunt Club Rd north of Washington St.
  • PCC sidewalk placement on the south side of Washington St east of Hunt Club Rd and the west side of Hunt Club Rd south of Washington St.
  • Stage 2 MOT shift